Wk Date Tech Milestone Art & Tech Milestone
1 Mar 14 (Mo) Quickstart out Game project out
  Mar 16 (We)   Speed Dating
TEAM NAMES DUE
  Mar 20 (Su)   TREATMENT DOC DUE
2 Mar 23 (We) QUICKSTART DUE
Project 1 out
Concept and model review
3 Mar 30 (We)   Design, discuss Web site
  Mar 31 (Th) PROJECT 1 DUE
Project 2 out
 
  Apr 3 (Su)   GAME WEBSITE ONLINE
4 Apr 4 (Mo) MID-TERM EXAM  
  Apr 6 (We)   Import art assets into game, Demo tech
  Apr 7 (Th) PROJECT 2 DUE  
5 Apr 11 (We) Project 3 out  
  Apr 13 (We)   Import art assets into game, Demo tech
  Apr 14 (Th) TECH MILESTONE PRESENTATION  
6 Apr 19 (Tu)   (Thursday schedule)
ALPHA PRESENTATION
  Apr 20 (We)   Import audio assets into game
  Apr 21 (Th) No class (Project presentation day)
PROJECT 3 DUE
 
7 Apr 25 (Mo)   PLAYTESTING (in class)
  Apr 27 (We)   Discuss playtesting feedback for adjustments
  Apr 28 (Th) FINAL EXAM  
8 May 2 (Mo)   BETA PRESENTATION
BETA DUE