Aug 24 | First day of term |
Aug 24 | Project 1 out |
Aug 27 | Project 1a due |
Aug 29 | Project 1b due |
Aug 31 | Project 1c due |
Sep 01 | Project 2 out |
Sep 04 | Labor Day (no class) |
Sep 08 | Project 2 due |
Sep 11 | Project 3 out |
Sep 18 | Mid-Term Exam |
Sep 20 | Project 3 due |
Sep 21 | Project 4 out |
Sep 27 | Project 4 due |
Sep 28 | Project 5 out |
Oct 06 | Project 5 due |
Oct 09 | Project Pitch |
Oct 10 | Game Fest |
Oct 12 | Final Exam |
Oct 12 | Last day of term |