Revised Details
The basic idea is that I have revised the Design sub-task and instead focused
on the deliverables of the implementation. Note that
- Individual
Assignment A1 worth 32 points
- 6 pts: Model -- Use Case Scenarios
- 6 pts: Analysis -- Class Diagrams
- 6 pts: Design -- Pseudo Code
- 8 pts: Testing Plan -- JUnit test cases
- 6 pts: Implementation and Packaging
- Final Exam worth 24 points -- Friday April 25th
There will be no make-up final exam
- Group
Project worth 44 points
20 pts: Analysis and
Design
20 pts: Implementation (Alpha
and Beta), Testing,
Documentation, and Packaging
4 pts: Fully Integrated Kombat
Solitaire Application
- 10 Pts: Analysis
- 8 pts: Beta
- 8 Pts: Documentation and Packaging
- 10 Pts: Testing (follow JUnit approach identified by
TestDevelopment)
- 8 Pts: Final implementation as fully integrated component in KS
application